New Premises

On 18th February 2008, I became the proud owner of a dilapidated wooden building known as "The Legion Hut".

          Old Legion Hut

I had grand designs for this building and you will see the progress in the photos below.



On 24th November 2008 work started on the site. The builder John Armstrong from Bentham secured the site by putting fencing all the way around it.

          Demolished

On a sunny Tuesday morning, 25th November, the demolition started and the old building was down by the Wednesday evening.



          Site levelled

By the end of the week the site was levelled and marked out ready for work to begin on the foundations for the new building.



          Digging out for the foundations



Digging out for the foundations




               Foundations



Foundations showing the room layout




          Level footings




Foundations ready to build on





          Beam and block flooring under construction



Beams for the beam and block flooring with one of the two windposts in the foreground



          Beam and Block almost completed



The blocks in place for the flooring




          Walls starting to grow



Breeze block walls starting to grow




          Jack choosing the next stone



Jack choosing the next stone for the facing





          Front door and window openings



Front window and door openings




          Scaffolding going up



Scaffolding going up




          Scaffolding in place


Scaffolding in place




          Scaffolding covered



Scaffolding covered so that the weather won't interfere with the building work


          Under cover



Working under cover




          Roof timbers being addd



Roof timbers being added




          View of the slate roof



Roof completed




          Upstairs landing



Upstairs landing looking towards my office




          Stairwell




Stairwell on a sunny day





          Preparing the walls for insulation



Preparing the outside walls for insulation




          Sheep's wool insulation



Sheep's wool insulation in place




          Reception and waiting room


Downstairs Reception and Waiting Area looking towards my treatment rooms



          Reception and waiting room plastered



Downstairs Reception and Waiting Area with the walls plastered




          Upstairs Room



The light and airy upstairs room for classes and courses and workshops




          Cedar cladding



Beautiful Cedar cladding at the front of the building






          The covers coming off



The wraps coming off





     The finished building



The completed building





     Mary Bowker cuts the ribbon to open the building


On 15th June 2009 the building was opened with the ribbon being cut by Mary Bowker, Marie's oldest patient. The dedication of the building was done by Pauline Turner, founder of International School of Awareness.



I am most grateful to the builder John L Armstrong and his team for working so hard to produce this wonderful building in six short months.

The joinery was done by Chris Brownsord of Bentham, the electrics by Neil Smith of Clitheroe, the plumbing by Martin Cowgill of Bentham, the plastering by M J Walker Plastering Ltd, the digging out by Lawsons Hazelwood Ltd, the floor screed by T B Construction Ltd  from Skipton, the roofing contractor was Andrew Broster from Hest Bank and the scaffolding was supplied by On Target Scaffolding.

Barbara Rothwell and Arthur of Bentham did the internal and external decorating.

Floor coverings were supplied by Malcolm Preece of Hash Browns in Bentham.

The signs have been made By vision Signs of Clapham.

The Construction Design and Management Coordinator was Dave Collins of Newmac Ltd of Killington.

The beautiful building design was done by Stephen Craven Building Design of Giggleswick. 

I wanted to produce the most environmentally friendly building practically possible.

The blocks for the wall are Enviroblocks, the stone was reclaimed from a mill in Bradford and the slates are reclaimed Burlington from Scotland and had only been in use for 20 years. The insulation is made from sheep's wool.

An airsource heatpump supplied by Ecohometec of Doncaster supplies the underfloor heating both upstairs and downstairs and a heat recovery ventilation system provided by Villavent of Witney ensures a minimal loss of heat from the building by recovering heat from expelled air and sending filtered, warmed air back into the building. The building has gained a B rating energy performance certificate.

My grateful thanks also to my family and friends who have supported and believed in my vision of a holistic centre of excellence for health and wellbeing and also to the HSBC bank for funding the project.